Corporate income tax holidays, import duty exemptions and land rent relief depend on specific zone classification, industry codes and project scale. Here are the key checks before signing an MOU.
1. Why tax incentives differ across industrial zones
During site selection in northern Vietnam, investors frequently receive marketing brochures quoting headline Corporate Income Tax (CIT) holidays. Under Vietnamese investment and tax laws, however, actual incentives do not apply uniformly across an entire province; they depend on the exact statutory zoning of the plot (Coastal Economic Zone versus standard Industrial Park) and registered industry codes.
In Quang Ninh, a manufacturing project located inside an industrial park within a designated Coastal Economic Zone qualifies for a different incentive structure than one in a standard industrial zone. The first step in any Pre-Feasibility Study (Pre-FS) is verifying the legal zoning boundary of the target plot.
2. Three incentive pillars to verify: CIT, import duties and land rent
To build an accurate 10-year cash-flow model, your finance team should separate three distinct statutory incentive pillars rather than relying on a single headline rate:
- Corporate Income Tax (CIT): Verify preferential tax rates, tax holiday years and 50% reduction years, paying close attention to the trigger point (first year of revenue versus first year of taxable profit).
- Import duty on fixed assets: Confirm exemption eligibility for machinery, production lines and specialized means of transport creating fixed assets, including strict technical rules if importing used equipment.
- Land rent versus infrastructure fees: Distinguish clearly between State land rent exemptions and commercial infrastructure sublease fees paid to the industrial park developer.

3. Qualifying conditions: sector, zone, scale and timeline
Supporting industries, high-tech manufacturing or large-capital projects may qualify for sector-based incentives independent of location. However, sector-based incentives often require post-licensing certification once the plant is operational.
When comparing candidate parks across Quang Ninh, Hai Phong and Bac Ninh, investors should place these conditions into a side-by-side matrix to see which incentives are recorded directly on the Investment Registration Certificate (IRC) and which require subsequent tax filings.
4. Common pitfalls & 6-step checklist before signing an MOU
The most common pitfall is assuming that the maximum incentive advertised in a brochure automatically applies to every VSIC activity code of your enterprise. Before signing an MOU or reservation deposit, complete these 6 verification steps:
- Step 1: Confirm exact VSIC industry codes and HS product codes for your primary manufacturing lines.
- Step 2: Verify the industrial park's master zoning decree and environmental sector classification for the plot.
- Step 3: Separate location-based incentives from sector-based incentives requiring post-go-live certification.
- Step 4: Model 10-year total cost of occupancy including land lease, management fees, power, water and wastewater tariffs.
- Step 5: Audit plot handover readiness and actual substation/wastewater capacity at the tie-in point.
- Step 6: Embed conditions precedent (IRC issuance, utility handover) into the MOU protection clauses.
Need a review tailored to your specific dossier? Speak with An Tri.
Speak with a specialistDirectly related service:
Site Survey & Location Connection
Pre-feasibility studies, incentive comparisons and land or ready-built factory lease negotiations across northern Vietnam industrial parks.
An Tri Investment Advisory Desk
Investment promotion, legal compliance and industrial operations advisory team in northern Vietnam.