How do IRC and ERC differ? The legal roadmap for a new factory in Vietnam

Updated: 2026-11-026 min readAn Tri Legal & Licensing Desk
Document folder tied with ribbon and a brass company seal

Two certificates serving two distinct regulatory functions. Getting the sequence and overseas document legalization right prevents costly resubmissions.

1. What is an IRC and what is an ERC?

For foreign investors setting up a greenfield plant in Vietnam, the regulatory framework separates the 'Investment Project' from the 'Corporate Entity'. The Investment Registration Certificate (IRC) approves the project parameters: investor identity, manufacturing objectives, annual capacity, total investment capital, capital contribution schedule and project location.

The Enterprise Registration Certificate (ERC), by contrast, incorporates the local company and serves as its corporate tax identification number. For a new FDI project, the investor must secure the IRC first and then submit the IRC to obtain the ERC.

2. Foundation documents: consular legalization and financial proof

The critical path in licensing often lies in preparing and legalizing parent-company documents overseas. Certificates of incorporation, corporate charters, two years of audited financial statements or bank balance confirmations must be notarized, authenticated by the home country's foreign affairs authority and consular-legalized for use in Vietnam.

Any discrepancy in investor name spelling, registered address or authorized signatory across documents will trigger clarification requests during IRC review.

Legal document folder, company seal and pen on a dark walnut desk
Legal document folder, company seal and pen on a dark walnut desk

3. Mandatory steps immediately after receiving the ERC

Holding the IRC and ERC does not yet allow capital injection. The newly formed company must complete post-incorporation setup within the statutory charter capital contribution window (typically 90 days from ERC issuance):

  • Carve the official corporate seal.
  • Open a Direct Investment Capital Account (DICA) at ONE licensed bank in Vietnam — all charter capital injections and offshore shareholder loans must flow exclusively through this DICA.
  • Open local currency and foreign currency current accounts for daily operational disbursements.
  • Register a digital tax signature token, complete initial tax registration and activate electronic invoicing.

4. Common mistakes that force early license amendments

In practice, three frequent errors force investors to file IRC amendments within their first year: (1) Omitting trading, import or export distribution rights alongside core manufacturing objectives; (2) Defining product capacity units or HS classifications too narrowly compared to actual production lines; and (3) Wiring capital from the wrong overseas entity or into an operating account prior to DICA activation.

Cross-reviewing the draft IRC across legal, tax and customs teams before submission prevents weeks of remedial amendments later.

Need a review tailored to your specific dossier? Speak with An Tri.

Speak with a specialist
This content is for general informational purposes only and does not constitute formal legal advice for a specific project. Please contact An Tri for a review tailored to your project dossier.

Directly related service:

Legal & Investment Licensing

Consular legalization, corporate establishment, IRC/ERC licensing, corporate seals and direct investment capital accounts.

An Tri Legal & Licensing Desk

Investment promotion, legal compliance and industrial operations advisory team in northern Vietnam.

About

Related Insights

View all insights
Interior of a modern factory with an illuminated aisle

Preparing a project in Vietnam?

Send us your project parameters — An Tri responds within 24 business hours in your preferred language.