Determining the exact environmental dossier required during the basic design phase saves months on your critical path and avoids post-construction retrofits.
1. Two regulatory instruments at different project milestones
Under Vietnam's Law on Environmental Protection, industrial manufacturing projects are classified into groups based on environmental impact risk, production scale and location sensitivity. This classification dictates whether a project must complete an Environmental Impact Assessment (EIA / ĐTM), obtain an Environmental Permit (GPMT), or file an Environmental Registration.
Crucially, an EIA (when required) must be appraised and approved before construction permitting milestones, whereas the Environmental Permit is the operational prerequisite for trial commissioning of waste treatment facilities and commercial production.
2. Technical parameters that determine your environmental category
An environmental category cannot be determined merely from a generic industry title such as 'electronics assembly' or 'metal fabrication'. Your advisory team needs four specific technical inputs from your process engineers:
- Detailed process flow: Does the line include electroplating, wet painting, chemical degreasing, wave soldering or surface treatment?
- Maximum annual design capacity (measured in units or metric tons of output/input).
- Daily domestic and industrial wastewater discharge volume (m3/day) relative to the industrial park's centralized WWTP acceptance standards.
- Estimated air emission flow rates, dust extraction requirements and monthly hazardous waste generation volumes.

3. Aligning environmental dossiers with civil and fire safety drawings
A frequent compliance bottleneck occurs when the plant layout submitted in the environmental dossier diverges from the drawings approved for fire safety or construction permitting — for example, relocating the hazardous waste storage room, pre-treatment tanks or exhaust stacks during construction.
When authorities conduct on-site verification prior to permit issuance, layout discrepancies can force physical alterations or dossier re-filings. An Tri cross-checks Environmental, Fire Safety and Construction submissions against a single master architectural layout.
Need a review tailored to your specific dossier? Speak with An Tri.
Speak with a specialistDirectly related service:
Environment, Fire Safety & Operating Conditions
EIA / Environmental Permits, fire safety design appraisal and acceptance, and construction permits.
An Tri Environment & Compliance Desk
Investment promotion, legal compliance and industrial operations advisory team in northern Vietnam.





