Fire safety design appraisal and acceptance: pre-go-live checklist

Updated: 2026-11-045 min readAn Tri Technical & Fire Safety Desk
Engineer inspecting a fire alarm control panel

Fire safety approvals are frequently delayed by incomplete drawings, uncertified equipment substitutions or field installations that deviate from appraised designs.

1. Design appraisal versus final fire safety acceptance

Fire prevention and fighting (PCCC) compliance for industrial plants consists of two mandatory gates: (1) Fire Safety Design Appraisal on engineering drawings prior to installation; and (2) On-Site Fire Safety Acceptance testing after installation and full system interlocking are complete.

Whether you build a new facility from scratch or lease a ready-built factory and install cleanrooms, mezzanine partitions, chemical storage or higher-fire-load machinery, you must verify whether a design modification appraisal is required before fit-out.

2. Frequent discrepancies that delay acceptance

Under tight schedules to meet machinery arrival dates, MEP or fit-out contractors sometimes shift partition walls, sprinkler heads or exit signage, or install fire-rated materials lacking valid inspection certificates.

During final acceptance, inspectors compare the physical installation and equipment inspection certificates directly against the stamped appraisal drawings. Any deviation in egress widths, structural steel fireproofing or pump station pressure must be rectified before the acceptance certificate is issued.

3. Pre-acceptance fire safety checklist before Go-Live

To ensure a smooth official inspection, project teams should conduct an internal mock acceptance test covering these items at least two weeks ahead of the scheduled inspection:

  • Verify 100% alignment between physical partitions, fire doors, egress corridors and the stamped appraisal drawings.
  • Compile all statutory fire equipment inspection certificates and stamps for pumps, control panels, detectors, extinguishers and fire doors.
  • Audit structural steel intumescent fireproofing application logs and dry-film thickness test records.
  • Run full-system interlock tests: alarm trigger -> power cut-off -> smoke extraction / stairwell pressurization -> fire pump activation.
  • Establish the plant fire safety team, post fire regulations and install evacuation maps across all zones.

Need a review tailored to your specific dossier? Speak with An Tri.

Speak with a specialist
This content is for general informational purposes only and does not constitute formal legal advice for a specific project. Please contact An Tri for a review tailored to your project dossier.

Directly related service:

Environment, Fire Safety & Operating Conditions

EIA / Environmental Permits, fire safety design appraisal and acceptance, and construction permits.

An Tri Technical & Fire Safety Desk

Investment promotion, legal compliance and industrial operations advisory team in northern Vietnam.

About

Related Insights

View all insights
Interior of a modern factory with an illuminated aisle

Preparing a project in Vietnam?

Send us your project parameters — An Tri responds within 24 business hours in your preferred language.